– Buried prefabricated reinforced concrete reservoir with a capacity of 1,000 m3.
– Buried prefabricated concrete pumping station.
– 600 m of HDPE pipe DN350 mm PN10 atm.
– 190 m of HDPE pipe DN200 mm PN10 atm.
– 2 pumps capable of pumping 54 m3/h to a height of 90 m.
– 2 pumps capable of pumping 90 m3/h to a height of 60 m.
– 2 pumps capable of pumping 5 m3/h to a height of 90 m.
– 1 pump capable of pumping 5 m3/h to a height of 60 m.
– Associated valves and pipework.
– Monitoring and control of the works.
– Health and safety coordination.
– Technical assistance support to the project.
– Quality control monitoring.
– Geometric, material and works execution control.
– Economic control.
– Works surveillance.
– Drafting of the as-built project.